Lac du Bonnet Personal Care Home
New two-story 95 bed personal care home, utilizing household design concept
Project Details
- Contains seven typical households with 12 standard resident bedrooms, and one household with nine standard resident bedrooms and two bariatric resident bedrooms. Design includes small groupings of resident rooms in self-sufficient households with dedicated kitchens, dining and living areas along with support facilities.
- Replaces the existing 30 bed PCH, resulting in 65 net new beds.
- New PCH footprint will be 84,300 ft2 (current PCH is 23,700 ft2).
- The facility and building will be owned and operated by the IERHA.
- Construction scheduled for completion in Fall 2027.
Staff and community members are welcome to email any project questions to [email protected].
Architectural Renderings




Construction Status
Project Milestones
- Construction site preparation – December 2024
- Excavation – February 2025
- Procurement – Winter 2026
- Critical path construction items – all superstructure components, includes masonry, structural steel, and precast concrete